1 Préparer l'installation

Have the gateway, KNX bus connection, 12-30 VDC auxiliary supply, network connection, ETS application and inverter configuration access ready. Check compatibility and firmware in Sections 3 and 10.

2 Raccorder et alimenter la passerelle

Connect KNX at the top. Connect auxiliary power and RJ45 Ethernet at the bottom. Connect the equipment to the same local network. The green Network LED confirms the Ethernet link; see Section 3.

3 Configurer la connexion de l'onduleur

Enable Modbus TCP or configure the required inverter connection using Section 4. Confirm the inverter address, port and Unit ID.

4 Régler le réseau et la liaison Modbus

Open 192.168.1.51 from a laptop on a compatible network and assign an appropriate fixed gateway IP address. Set Mode to Connect, Server IP to the inverter address, Server Port to 502 and Unit ID to 1.

5 Configurer l'appareil KNX dans ETS

Assign a free physical address. Set Inverter model to 3 for Fronius including Gen24; 6 for Fronius Symo Hybrid. Set the AC network, applicable PV circuits, refresh rate and available equipment. Set Device Options to the Fronius Smart Meter Modbus ID when a meter is installed; check the actual ID (default 200 or 240). See Sections 5 and 6.

6 Lier les adresses de groupe et télécharger

Assign group addresses to the required objects. Press P when ETS requires programming mode and perform a full application download for initial commissioning. See Section 5.

7 Valider les données et activer la logique

Check the Connected LED and Module status (GO 1 = 0). Read firmware (GO 2), wait for the polling interval and compare live values with the inverter. Check power directions and optional equipment before enabling logic. See Section 7.

Commissioning is complete when

The network and inverter links are established, the ETS download succeeds, and the required group objects return plausible values for the installed equipment.

All chapters of the INV-KNX Fronius user manual

Questions fréquentes

Que faut-il préparer avant la mise en service ?

Préparez la passerelle, une alimentation auxiliaire 12–30 VDC, le bus KNX, les connexions réseau, l'application ETS et l'accès à la configuration de l'onduleur.

Le voyant Network prouve-t-il que la mise en service est terminée ?

Non. Le voyant Network confirme la liaison Ethernet physique. Vérifiez aussi Connected, terminez le téléchargement ETS et comparez les valeurs KNX avec l'onduleur.

Quand activer l'automatisation basée sur les données de l'onduleur ?

Vérifiez l'état du module, attendez l'intervalle d'interrogation, comparez les mesures et contrôlez les sens de puissance ainsi que les équipements optionnels.

Continuer l'exploration

Retrouvez les autres guides de ce produit dans la documentation.

Retour à Manuel d'utilisation INV-KNX Fronius