Comissionamento rápido

Sequência de comissionamento do INV-KNX SMA, desde a cablagem até à validação das medições KNX.

elausys · 10 setembro 2026
Nesta página

Follow these steps in order. For a new installation, use inverter model 23 with gateway Modbus Unit Id 3. Use model 1 only for the legacy cases described in Section 3.

1 Prepare the installation

Have the INV-KNX gateway, a 12-30 VDC auxiliary supply, KNX bus connection, Ethernet connection, ETS with the appropriate Elausys application and SMA installer access ready. Record the inverter IP address and choose a free gateway IP address on the same network.

2 Connect and power the gateway

Connect KNX at the top. Connect the auxiliary supply and Ethernet at the bottom. Keep the gateway and inverter on the same router/network. Check that the green Network LED indicates a physical Ethernet link. See Section 3.

3 Enable Modbus TCP on the inverter

Log in as Installer. Enable Modbus > TCP Server, select Activated = Yes and use port 502. Save the inverter configuration. The Sunny Explorer procedure is in Section 4.

Open the gateway at 192.168.1.51 from a laptop on a compatible network. Assign a suitable fixed IP address. Set Mode = Connect, IP = inverter IP address, Server Port = 502 and Unit Id = 3 for model 23 or 126 for model 1. Always target the inverter, not Sunny Home Manager.

5 Configure the KNX device in ETS

Assign a free physical address. Set the inverter model, AC network, one or two PV circuits and refresh interval. Enable Battery 1 and Powermeter only when present. Leave Battery 2 as Not Used and Device Options empty. See Sections 5 and 6.

Assign a group address to every required group object. Press P for programming mode when assigning the physical address; perform a full download for the first commissioning. Include the configured application and group-address links. See Section 5.

7 Validate the data before enabling logic

Check the Connected LED. In ETS Group Monitor, verify Module status = 0 and compare live inverter data after the configured polling interval. For model 23, check battery power and grid power signs. Record the configuration and firmware. See Section 7.

Commissioning is complete when

Both Ethernet and inverter communication are established, the ETS download succeeds, the required group objects return plausible values and the installed equipment matches the enabled battery and meter options.

Manual navigation

All chapters of the INV-KNX SMA user manual

Perguntas frequentes

O que deve estar preparado antes do comissionamento?

Prepare a gateway, uma alimentação auxiliar de 12–30 VDC, as ligações KNX e de rede, a aplicação ETS adequada e o acesso à configuração do inversor.

O LED Network prova que o comissionamento está concluído?

Não. O LED Network confirma a ligação Ethernet física. Verifique também a comunicação com o inversor através do LED Connected, conclua o download ETS e compare os valores KNX necessários.

Quando devo ativar a automação baseada nos dados do inversor?

Verifique primeiro Module status, aguarde o intervalo de polling configurado, compare as medições em tempo real e confirme os sentidos da potência e o equipamento opcional.

Continuar a explorar

Encontre os outros guias deste produto na documentação.

Voltar a Manual do Utilizador INV-KNX SMA