Quick commissioning

The commissioning sequence for INV-KNX SMA, from wiring to validated KNX measurements.

elausys · 10 September 2026
On this page

Follow these steps in order. For a new installation, use inverter model 23 with gateway Modbus Unit Id 3. Use model 1 only for the legacy cases described in Section 3.

1 Prepare the installation

Have the INV-KNX gateway, a 12-30 VDC auxiliary supply, KNX bus connection, Ethernet connection, ETS with the appropriate Elausys application and SMA installer access ready. Record the inverter IP address and choose a free gateway IP address on the same network.

2 Connect and power the gateway

Connect KNX at the top. Connect the auxiliary supply and Ethernet at the bottom. Keep the gateway and inverter on the same router/network. Check that the green Network LED indicates a physical Ethernet link. See Section 3.

3 Enable Modbus TCP on the inverter

Log in as Installer. Enable Modbus > TCP Server, select Activated = Yes and use port 502. Save the inverter configuration. The Sunny Explorer procedure is in Section 4.

Open the gateway at 192.168.1.51 from a laptop on a compatible network. Assign a suitable fixed IP address. Set Mode = Connect, IP = inverter IP address, Server Port = 502 and Unit Id = 3 for model 23 or 126 for model 1. Always target the inverter, not Sunny Home Manager.

5 Configure the KNX device in ETS

Assign a free physical address. Set the inverter model, AC network, one or two PV circuits and refresh interval. Enable Battery 1 and Powermeter only when present. Leave Battery 2 as Not Used and Device Options empty. See Sections 5 and 6.

Assign a group address to every required group object. Press P for programming mode when assigning the physical address; perform a full download for the first commissioning. Include the configured application and group-address links. See Section 5.

7 Validate the data before enabling logic

Check the Connected LED. In ETS Group Monitor, verify Module status = 0 and compare live inverter data after the configured polling interval. For model 23, check battery power and grid power signs. Record the configuration and firmware. See Section 7.

Commissioning is complete when

Both Ethernet and inverter communication are established, the ETS download succeeds, the required group objects return plausible values and the installed equipment matches the enabled battery and meter options.

Manual navigation

All chapters of the INV-KNX SMA user manual

Frequently Asked Questions

What must be ready before commissioning?

Prepare the gateway, a 12–30 VDC auxiliary supply, the KNX bus and network connections, the appropriate ETS application, and access to the inverter configuration.

Does the Network LED prove that commissioning is complete?

No. The Network LED confirms the physical Ethernet link. Also check inverter communication with the Connected LED, complete the ETS download and compare the required KNX values with the inverter.

When should I enable automation based on inverter data?

First verify Module status, wait for the configured polling interval, compare live measurements and check power directions and optional-equipment availability.

Keep exploring

Find the other guides for this product in the documentation.

Back to INV-KNX SMA User Manual